施工的一般规定
General provisions for construction
1.外保温工程施工期间以及完工后24h内,基层及环境空气温度不应低于5℃。夏季应避免阳光暴晒。在5级以上大风天气和雨天不得施工。
1. During the construction of external thermal insulation project and within 24 hours after completion, the temperature of base course and ambient air shall not be lower than 5 ℃. Avoid sun exposure in summer. Construction is not allowed in windy weather and rainy days above level 5
2.保温工程实施前应编制专项施工方案并经监理(建设)单位批准后方可实施。施工前应进行技术交底,施工人员应经过培训并经考核合格。
2. Special construction scheme shall be prepared and approved by the supervision (construction) unit before the implementation of thermal insulation works. Technical disclosure shall be carried out before construction, and construction personnel shall be trained and qualified through assessment
3.保温砂浆工程的施工应在基层施工质量验收合格后进行。避免在潮湿的墙体上做保温层。原墙面为加气混凝土成马赛克、面砖等旧墙面时,需做专门的界面处理。
3. The construction of thermal insulation mortar works shall be carried out after the base construction quality acceptance. Avoid insulation on wet walls. When the original wall is made of aerated concrete into mosaic, face brick and other old walls, special interface treatment is required.